Connect with us

India

Gujarat Leg Of Bullet Train May Start If Maharashtra Land Issues Not Resolved: Official

Bullet train may start in Gujarat first, an official said.

Ahmedabad:

The National High Speed Rail Corporation Limited (NHSRCL) on Thursday said the Gujarat leg of the Ahmedabad-Mumbai bullet train may open first if it could not acquire land in Maharashtra in the next three months.

Project official Achal Khare also said at a virtual press meet that the deadline of 2023 for completing the project was not feasible, and civil works on Gujarat side were expected to be completed by 2024.

The NHSRCL has acquired 95 per cent of the land for the 352-km stretch of the project in Gujarat, but has been able to acquire only 23 per cent of land for the 156-km stretch in Maharashtra.

“Of the 352-km stretch, we have acquired 95 per cent of land thanks to the cooperation of people as well as the Gujarat government,” Mr Khare said, adding that the remaining five per cent will be acquired by mid-June.

“The NHSRCL has been able to acquire 23 per cent land so far in Maharashtra. If we are able to acquire about 70 per cent to 80 per cent land in the next three months, we can start the entire project together,” he said.

If not, the NHSRCL will have to consider opening the Gujarat leg of the bullet train in the first phase and the Maharashtra leg in the second phase, he said.

“There are many issues over land acquisition in Maharashtra. We are in talks with our Japanese counterparts to open the Gujarat phase of the project first,” Mr Khare said.

The Uddhav Thackeray-led MVA government in Maharashtra had said that it will review the “necessity of the project” after coming to power.

For the Gujarat leg of the project, contracts worth Rs 32,500 crore have been awarded for the construction of 325 km stretch and five stations, Mr Khare said.

The bullet train will have eight stations in Gujarat and four in Maharashtra.

“Tenders for Sabarmati and Ahmedabad stations and 18 km stretch in that city will be released on March 25, while those for Vadodara station and 7 to 8 km stretch in that city will be released in June,” Mr Khare said.

“The original deadline of completing the project in 2023 is not feasible as a year was lost due to the COVID-19 pandemic and land acquisition issues in Maharashtra,” he said.

“We expect to complete the civil works on the Gujarat side in four years, by 2024,” he said.

The NHSRCL will need 24 sets of rolling stock for high-speed trains, of which 18 will be imported from Japan, while six will be manufactured in India.

“Japan has agreed to allow manufacture of six sets of rolling stocks in India. The manufacturer in Japan will tie up with an Indian company and make them here under the “Make in India” initiative. Talks are underway,” Mr Khare said.

Source link